ANTICIPATED PROJECT SCHEDULE
 
Milestone Date Status
Notice to Proceed July 29, 2010 Issued
Baseline Hydrology Report January 2011 Accepted
Draft Alternatives Evaluation Report November 2015 Completed
Public Open House February 2016  
Final Alternatives Evaluation Report April 2016  
Draft Conceptual Design Report June 2016  
Final Conceptual Design Report September 2016